© copyright Sime Darby London Limited - Images by Chris Evans of Redwood Films
Regeneration of the Lec site
December 2012
Completion
October 2012
Finishing touches
September 2012
Store, petrol station and new access progressing
August 2012
Store, petrol station and new access taking shape
July 2012
Petrol station and new access construction commences
June 2012
Store construction commences
May 2012
Piling
April 2012
Completion of the Remediation Works
January 2012
Green Topper Site Remediation
December 2011
Final Site Clearance
November 2011
Bridge Removal
Admin Block Demolition
October 2011
LEC site Before and After top shots
Bridge Strip Down
A-Stores
Technical Block
Boiler House
Main Factory
Admin Block
Aerial Overview - Before and After
Celebration Event - Saturday 23rd July 2011 (Images by Jill Woodruff)
|